Oxygen Unit Installation - Update - Delivery of HFNC and O2 Regulators
Project Implementation - Status update 2:
Gas World has now finished the installation of 12 x O2 outlets at ward 4 and 2 x O2 outlets the preliminary care unit (PCU). The balance 6 are to be installed at ward 7; however there are already Covid patients there, hence, the hospital needs to move these patients out and thoroughly disinfect the ward before they can get Gas World to go in there.
This may take a few days as per Dr. Eranga. But he's happy to have 14 up and running on Monday, 24th May 2021.
We will go on Monday morning with the HFNC unit and the regulators and officially hand those over.
The balance 13 regulators - originally scheduled to arrive on Saturday are delayed as the flight carrying it from UK has been delayed. Hopefully this also will be in hand by Monday
Stay tuned for next update by EOD Tuesday!