Friday, July 24, 2009

Construction progress inspection - 23rd July 2009

Rtn. Nilesh inspecting the bathing area


Rtn. Nilesh inspecting the newly constructed temporary toilets

Water trough


Bio Gas/ Waste Management Plant being completed


Status Update - 23rd July 2009

Rotarians Nilesh and Prabhu from RCCR visited the IDP Camps to assess the construction progress of the Temporary Toilets and Bio Gas/ Waste Management Plants on Thursday 23rd July 2009.

Refer Masterplan (Earlier Post)

Toilets: Requirement 140 nos.

Block 6a (Front) : 20 Toilets in operation
Block 6a (Back) : 40 Toilets (to be connected to the Waste Management plant, all toilets constructed and pending connection to plant) (includes 4 disabled toilets)
Block 6b (Front) : 25 Toilets in operation
Block 6c (Front) : 15 Toilets in operation
Block 6c (Back) : 40 Toilets constructed (operational in 1 day)

Water troughs for cleaning of toilets: Requirement 5

Block 6a (Front) : Constructed and in operation
Block 6a (Back) : Constructed pending water connection
Block 6b (Front) : To be constructed (operational in 3 days)
Block 6c (Front) : To be constructed (operational in 3 days)
Block 6c (Back) : Construction in progress (1 days to complete)

Waste Management Plant: Requirement 2

Construction in progress, estimated time for completion 8 days


Bathing areas (showers and above ground water tanks): Requirement 3 Shower bays of 10 showers each and 3 above ground water tanks (30' x 3')

Block 6a (Front) : Shower bays Constructed and in operation / above ground water tanks to be constructed.
Block 6b (Front) : Shower bays Constructed and in operation / above ground water tanks to be constructed.
Block 6c (Front) : Shower bays Constructed and in operation / above ground water tanks to be constructed.

Tube Wells: Requirement 4

Location to be decided on yeild of water. Investigate in progress

Medical Centre: Requirement 1

Construction in progress, estimated time for completion 4 days